The new office development being constructed for Brookgate at 30 Station Road in Cambridge, has now had the last of its concrete pours completed on the 6th floor and on the roof. On the lower three floors of this building the construction of the steel framing system and concrete boarding has already commenced and the windows started to be installed.

By Christmas the team aim to have the concrete frame fully complete across the building, the roof finished and have progressed well up the sides of the building in order to start works on the internals of this project in the New Year.